The Improvement Works at Tai O are being implemented in 3 phases with a view to enhancing the local infrastructure to address the most pressing needs of Tai O residents, enhancing traffic and pedestrian circulation and providing additional parking spaces at Tai O.

Scope of Works

Phase 1 works include:

  1. Construction of a riverwall at Yat Chung and the associated drainage and sewerage improvement works;
  2. Upgrading of the temple garden in front of Kwan Tai Temple; and
  3. Improvement to the signage within the inner-core area of Tai O.

Phase 2 Stage 1 works include:

  1. Construction of a public open space, a public transport terminus, a public car park for private cars, a loading and unloading area, a cycle parking area and associated roadworks at the western end of Tai O Road;
  2. Provision of on-street parking spaces for coaches and goods vehicles at Lung Shing Street in Yim Tin; and
  3. Landscaping and ancillary works.

Phase 2 Stage 2 works include:

  1. Construction of footbridges at Po Chue Tam and Yim Tin;
  2. Upgrading works of the open area in front of Yeung Hau Temple;
  3. Construction of an amphitheatre-cum-open space and a public car park at Yim Tin; and
  4. Ancillary works, including associated road, drainage, water mains, sewerage, utilities, landscaping and public lighting works, etc.

Phase 3 works include:

  1. Construction of a promenade and a garden at Shek Tsai Po;
  2. Construction of a footbridge to connect the proposed promenade and the existing Tai O public transport terminus;
  3. Improvement to the existing helipad;
  4. Provision of information and directional signage for inner loop heritage trail and outer loop nature trail;
  5. Improvement of existing roads and streetscape within the Tai O inner-core area; and
  6. Other supporting infrastructure including refuse collection point and upgrading/ extension of water reticulation system, etc.

Programme

Phase 1
Completed

Phase 2 Stage 1
Completed

Phase 2 Stage 2
Under construction

Phase 3
Under Detailed Design

Current Progress

Phase 1
Construction for the works was completed (under PWP Item 7435RO).

Phase 2 Stage 1
Construction for the works was completed (under PWP Item 7469RO).

Phase 2 Stage 2
Construction of the works (under PWP Item 7483RO) commenced in March 2023. The works are expected to be completed in about 3 years.

Phase 3
The works are under detailed design stage.